|

K.B.
Clarke restores Bedford townhouse complex after extensive fire damage.
After a large
fire developed, affecting several units of a semi-detached housing
complex located in Bedford in December, 2001, K.B.
Clarke was called by three separate insurers to provide emergency
restoration services and later reconstruction for each of the owners.
To control the spread of flames and minimize damages, the fire department
called in an excavation contractor to knock down part of the middle
unit. There was a lot of water used to extinguish the flames, which
created huge structural and water damage problems for the adjacent
units and totally destroying the affected unit.
After the fire
and investigation was completed, the first step was to arrange the
completion of the dismantling and disposal of debris without further
secondary damage to adjacent units. This was started after an extensive
hazard assessment for worker safety and great cooperation between
trades to carefully remove parts of the framing from adjacent units
by hand, then use an excavator with a retractable arm to grab the
debris and remove it
(see photos 1 & 2).
This was completed in two days and the next step was to stabilize,
insulate and waterproof the newly exposed walls of the two adjacent
units to prevent freeze ups and additional water infiltration
(see photo 3).
While the securing
of the exterior was being done, K.B. Clarke had simultaneous crews
inside several units, inventorying, packing and moving all contents
to their Dartmouth warehouse for drying, dehumidification and cleaning.
The contents then remained in storage while crews started the removal
of thousands of square feet of drywall, insulation, flooring, etc.
at the job site. After the units were thoroughly dried, K.B. Clarke
project manager Steve Hagen arranged for deodorization, smoke sealing
and the reconstruction inside of the units, while Jamie Geddes,
the Cleaning Manager was reviewing the condition of contents with
the owners.
This went very
quickly and at the same time K.B. Clarke arranged plans for reconstruction
of the destroyed unit. This was then put out to tender and K.B.
Clarke provided the most competitive quote for reconstruction. Before
this reconstruction even started, K.B. Clarke had completed interior
repairs of the adjacent units with drywall, painting and flooring
replaced, all contents were returned and set up for the owners to
be back in for the Christmas holidays.
After the building
permit was obtained and a structural engineer confirmed stabilization
of the firewalls, K.B. Clarke started reconstruction in the cold,
frigid and snowy month of February. The unit was roof tight despite
terrible weather by mid - March and totally completed by May 2002
(see photos 4 & 5).
|





|